Regulations
Regulation 53 of the Public Contracts Regulations 2015 requires an organisation subject to the EU procurement rules to offer on the internet, “unrestricted and full direct access free of charge to the procurement documents from the date of the publication” [of the OJEU notice].
“Procurement documents” is defined in Regulation 2 and includes the contract terms, specification, payment mechanism and key performance indicators, the invitation to tender documentation and tender submission requirements.
You could be forgiven for having thought that this was pretty clear. There were some issues around whether it was legitimate to require prospective tenderers to register before giving them access to the procurement documents and over how this Regulation was intended to operate in procedures such as competitive dialogue where the documents are developed through the dialogue stage. However, there was no suggestion that you could be excused from making some of the procurement documents available, at least in some draft minimally developed format.
CCS Guidance
Then along comes the Cabinet Office to change this view, in the form of the Crown Commercial Service (“CCS”) Guidance on Electronic Purchasing and Electronic Communications [1].
This guidance fundamentally changes the nature of the debate on this Regulation. On page 13 that guidance (when talking about the restricted procedure) says that, “CCS take the view that …where individual regulations refer to “procurement documents”, what is meant by that wording changes based on the different stages of the process that has been reached.
In other words, the CCS are saying that the meaning of the words “procurement documents”, as defined in Regulation 2, is different in different Regulations. Where the “procurement documents” are referred to in Regulation 53, they seem to be saying that this does not include documents that have not been produced before the OJEU notice is submitted.
The guidance goes on, “As the procurement and competition become more crystallised, CCS expect more of the documents falling within that wide definition of procurement documents to be generated and therefore supplied. In contrast, at very early stages, fewer of the documents, if any, would be included.”
This approach does seem rather to have come from the “Humpty Dumpty School of Interpretation” [2]. It also appears to be contradicted by the October update of the CCS Brief Guide to the EU public contracts Directive [3]. This repeats the wording from the February 2015 version to say that, “Electronic versions of the procurement documentation must be available through an internet URL immediately on publication of the OJEU contract notice.”
Where further procurement documents are added “as and when they are developed”, they are clearly not “available…immediately.”
Risk analysis
The real question here, though, is not so much whether the CCS are right, but whether you can follow their guidance on “Electronic Procurement” with impunity.
Assuming that it is a breach of the Regulations not to make the procurement documents available before submitting the OJEU notice, this breach will occur when the OJEU notice is published. A disgruntled tenderer would then have 30 days from that point to bring a challenge. As long as sensible time limits are used in the tender process, it is unlikely that any tenderer will have been excluded from the procurement process within that time. Since tenderers only tend to think about challenges after they have “lost”, it is very unlikely in practice that anyone would challenge here.
Other challenges are possible, but still unlikely to succeed. Whilst a tenderer could complain to the Mystery Shopper scheme, since this is handled by the Cabinet Office, they are hardly going to criticise an organisation that follows their own guidance!
The only area to be concerned about is if the procurement is for works, services or supplies part funded through EU grant. If the European Commission takes a different view to the CCS here, a failure to make the procurement documents available from the date of publication of the OJEU notice could be regarded as a breach that leads to a clawback of that European grant.
We would still recommend that you do draft the procurement documents “up front”, as this is good procurement practice. However, there is now support from the Cabinet Office for those that choose not to do so.
[1] Crown Commercial Service Guidance on Electronic Purchasing and Electronic Communications published in September 2015
[2] “When I use a word”, Humpty Dumpty said, in rather a scornful tone, “it means just what I choose it to mean – neither more nor less.” “The question is,” said Alice, “whether you can make words mean so many different things.” – Lewis Carroll 1832-98, Through the Looking Glass, Chapter 6.
[3] Crown Commercial Service Guidance A Brief Guide to the EU Public Contracts Directive (2014) October 2015 version
For advice on EU procurement issues please contact Andrew Millross .
Latest news
Anthony Collins advised B3Living on strategic acquisition of 250 social homes
The social housing team at Anthony Collins advised Hertfordshire-based B3Living on the successful acquisition of 250 social homes from Orbit Group.
Tuesday 19 November 2024
Read moreAnthony Collins promotes and appoints 19
19 promotions and appointments have been announced including two partners, two legal directors, two senior associates and four associates, as well as a number of appointments within the central management […]
Monday 4 November 2024
Read moreLatest webinars and podcasts
Podcast: Who gets the microwave? Episode 2 – Non-court dispute resolution
Listen to the second in a series of podcasts from our matrimonial team where Tom Gregory, Chris Lloyd-Smith and Maria Ramon put down their litigation weapons and discuss the importance of […]
Friday 22 November 2024
Read morePODCAST: Who gets the microwave?
The first in a series of podcasts from our matrimonial team begins with the team discussing what happens to pets during divorce and separation.
Friday 16 August 2024
Read more