Final accounts may mark the end of the delivery phase, but risks remain that must be managed appropriately to avoid disputes.
In the fifth part of our series on contract management pitfalls, we look at the risks associated with the final account process under construction contracts.
Most construction contracts will include a mechanism for the final valuation of works. Final accounts are, very much as the name suggests, the final valuation of the works delivered by the contractor, and account for extensions of time or delays. Contracts rarely specify the format in which a final account must be presented, but they frequently set out a timeframe in which the final account must be prepared and issued to the contractor.
While for many contracts, calculating the final account is be a straightforward exercise, we frequently see disputes arising out of the final account process, particularly where the contractual timetable for issuing the final account has not been followed, or where the final account is not clear as to how the valuation has been calculated. A lack of clarity around the valuation of contractor’s claims and the reasons why claims have been valued or rejected is a particular trigger point for final account-related disputes.
In our experience, providing a final account that is not sufficiently clear, or providing it out of time, can have the effect of hardening a contractor’s position in respect of claims they may have otherwise resolved pragmatically, and can also result in contractors submitting their own final account (often showing a much higher value than that assessed by the employer!) and referring the disputed sums to adjudication.
How to manage the risk?
Whilst social housing providers cannot always prevent claims from arising, there are some important steps that can be taken to reduce the risk of a final account dispute, and place providers in a good position to defend a claim should that become necessary:
- During delivery of the works and services, ensure that the interim payment mechanism is administered consistently, as this will provide a clear audit trail for preparing the final account;
- Similarly, responding to contractor’s requests for additional payment, loss and expense, and extensions of time, when those claims are made, will assist in preparing the final account;
- Ensure that the final account is issued within the time period required by the contract; and
- Finally, ensure that the final account is presented clearly and intelligibly. Pay particular attention to the valuing of changes, assessment of extensions of time or delays, and any claims raised by the contractor during the course of the works.
For more information
If you have any questions regarding the issues raised in this briefing or would like to find out more about our bespoke client training programme, please contact Andrew Lancaster.
Latest news
Anthony Collins advised B3Living on strategic acquisition of 250 social homes
The social housing team at Anthony Collins advised Hertfordshire-based B3Living on the successful acquisition of 250 social homes from Orbit Group.
Tuesday 19 November 2024
Read moreAnthony Collins promotes and appoints 19
19 promotions and appointments have been announced including two partners, two legal directors, two senior associates and four associates, as well as a number of appointments within the central management […]
Monday 4 November 2024
Read moreLatest webinars and podcasts
Podcast: Who gets the microwave? Episode 2 – Non-court dispute resolution
Listen to the second in a series of podcasts from our matrimonial team where Tom Gregory, Chris Lloyd-Smith and Maria Ramon put down their litigation weapons and discuss the importance of […]
Friday 22 November 2024
Read morePODCAST: Who gets the microwave?
The first in a series of podcasts from our matrimonial team begins with the team discussing what happens to pets during divorce and separation.
Friday 16 August 2024
Read more