In the third part of our series on contract management pitfalls, we look at the risks and opportunities presented by instructing changes under construction contracts.
Construction contracts will often contain mechanisms under which ‘changes’ or ‘variations’ can be instructed to the scope of works being delivered by a contractor, or the working conditions in which the works are delivered. There are many reasons why social housing providers may find it necessary to issue change instructions, and this can be a very useful mechanism. For instance, where additional works have been identified as being necessary following detailed surveys of properties, or where new property stock has been purchased and the new properties are to be included in the scope of works.
Instructing a change to the scope of works or working conditions does carry a number of risks, and we commonly see disputes arising out of change instructions. In our experience, there are two key themes:
- Is the change clear?
Change instructions need to be very clear as to what is being changed in the contractor’s scope of works, ensuring that both contractor and employer understand the extent of the change. Disputes often arise because the full consequences of the change has not been documented, or the parties had a conflicting understanding of what the change instruction meant. - Are the time and cost consequences agreed?
A change instruction will often entitle the contractor to additional time and cost, and it is of little surprise that many disputes relate to the extent of the additional time and cost due to the contractor. It is best practice to set out the full extent of the time and cost consequences in the change instruction, so that all parties are clear as to what additional payment will be made.
When used properly, change instructions can be a useful mechanism allowing social housing providers to react to fluctuations in their housing stock and address new construction needs as they are identified. That being said, there are risks associated with instructing changes, and those risks can be managed through carefully documenting the change, and the time and cost consequences.
We regularly deliver training to social housing providers in relation to instructing changes, contract management risks, and dispute resolution.
For more information
If you have any questions regarding the issues raised in this briefing or would like to find out more about our bespoke client training programme, please contact Andrew Lancaster.
Latest news
Anthony Collins advised B3Living on strategic acquisition of 250 social homes
The social housing team at Anthony Collins advised Hertfordshire-based B3Living on the successful acquisition of 250 social homes from Orbit Group.
Tuesday 19 November 2024
Read moreAnthony Collins promotes and appoints 19
19 promotions and appointments have been announced including two partners, two legal directors, two senior associates and four associates, as well as a number of appointments within the central management […]
Monday 4 November 2024
Read moreLatest webinars and podcasts
Podcast: Who gets the microwave? Episode 2 – Non-court dispute resolution
Listen to the second in a series of podcasts from our matrimonial team where Tom Gregory, Chris Lloyd-Smith and Maria Ramon put down their litigation weapons and discuss the importance of […]
Friday 22 November 2024
Read morePODCAST: Who gets the microwave?
The first in a series of podcasts from our matrimonial team begins with the team discussing what happens to pets during divorce and separation.
Friday 16 August 2024
Read more