Under most construction contracts, the contractor takes on the ground conditions risk.
The most regularly used standard form construction contracts reflect this; for example, the unamended Joint Contracts Tribunal (JCT) Design and Build Contract 2016 does not name adverse ground conditions as something that entitles a contractor to extra money or extra time. Well-drafted Schedules of Amendments specifically name the contractor as the party that takes the risk.
However, a recent case¹ has demonstrated that technical documents appended to a contract, such as a scope of works, can tip the risk back over to the employer.
In the case, E.ON had engaged Clancy Docwra Limited (CDL) to install some pipework. The scope of works, which was contained within the tender documents and appended to the contract², showed a clear pathway on the site through which the pipes could be installed. It later transpired that some underground brick rubble blocked the pathway.
CDL argued that the scope of works did require them to remove the rubble and that it was entitled to extra money to complete this task. E.ON argued that the contract (as amended by a Schedule of Amendments) contained clauses that specifically put the ground conditions risk on to CDL. E.ON also pointed to a priorities clause within the contract which stated that, in the event of inconsistencies between the Schedule of Amendments and other appended documents (including the scope of works), the Schedule of Amendments would prevail.
The Court decided that the ground conditions clauses in the contract only applied to CDL’s agreed scope of works but were not worded to extend the scope of works. As the scope document had expressly displayed a clear pathway for the pipework, the Court held that removing rubble from the pathway fell outside the scope and that CDL were entitled to extra money as a consequence.
The case highlights the importance of ensuring that all contract documents are consistent in terms of how they allocate the ground conditions risk.
Employer’s Requirements should be carefully drafted to ensure as far as possible that the scope of works includes dealing with adverse site conditions and that nothing negates or weakens the contractor’s obligation to do so without extra money or time.
For more information
If you would like to discuss this briefing further, please contact Richard Brooks.
Citations
1. Clancy Docwra Limited v E.ON Energy Solutions Limited
2. JCT Standard Building Sub-contract with sub-contractor’s design, 2011
Latest news
Anthony Collins advised B3Living on strategic acquisition of 250 social homes
The social housing team at Anthony Collins advised Hertfordshire-based B3Living on the successful acquisition of 250 social homes from Orbit Group.
Tuesday 19 November 2024
Read moreAnthony Collins promotes and appoints 19
19 promotions and appointments have been announced including two partners, two legal directors, two senior associates and four associates, as well as a number of appointments within the central management […]
Monday 4 November 2024
Read moreLatest webinars and podcasts
Podcast: Who gets the microwave? Episode 2 – Non-court dispute resolution
Listen to the second in a series of podcasts from our matrimonial team where Tom Gregory, Chris Lloyd-Smith and Maria Ramon put down their litigation weapons and discuss the importance of […]
Friday 22 November 2024
Read morePODCAST: Who gets the microwave?
The first in a series of podcasts from our matrimonial team begins with the team discussing what happens to pets during divorce and separation.
Friday 16 August 2024
Read more